    Construction Progress: July 2020

    30/07/2020

    Construction Progress: July 2020

    By Ivan A \ 5 Comments

    Despite the challenge of Covid-19 and an unusually wet season, site works are progressing according to schedule.

    Major Milestones achieved are:

    1. Wash Water Tower Base Cast
    2. Quay Completed and ready for GEF Barge Installation
    3. GEF Barge #1 arrived on site www.damen.com
    4. Submarine Cables arrived on site www.hengtonggroup.com
    5. Contractor Site Establishment Containers arrive
    6. Workboats GAJU and MBOGO launched
    7. Liebherr 70t and 250t cranes on site
    8. Piling Rigs for Power Plant arrive on site
    K56 Site – May 2020

    K56 Site – May 2020

    The K56 Technical Team visit to Ywama Power Plant – Myanmar with CES

    The K56 Technical Team visit to Ywama Power Plant – Myanmar with CES

    Piling Rig on Site and ready to commence piling

    Piling Rig on Site and ready to commence piling

     

    Wash Water Tower Foundation Bolts - Each Bolt weighs 38kg

    Wash Water Tower Foundation Bolts – Each Bolt weighs 38kg

    Assembly of Work Boat 2

    Assembly of Work Boat 2

    Share This Post

    RELATED POSTS

    COMMENTS

    1. online

      Thanks for sharing, this is a fantastic post. Really thank you! Much obliged. Jeanne Garald Verner

    2. filmkovasi

      These are really impressive ideas in about blogging. Luci Darcy Bloom

    3. 123movies

      This is my first time pay a visit at here and i am actually impressed to read all at single place. Tedra Hagen Gamages Margarethe Lowe Bittencourt

    4. netflix

      Really appreciate you sharing this blog article. Really looking forward to read more. Great. Peggy Juan Rotberg

    5. filmkovasi

      You have remarked very interesting points! ps decent site. Emmi Hanson Sheryle

    Leave a Reply

    Your email address will not be published.

    error: Content is protected !!