Construction Progress: July 2020
Despite the challenge of Covid-19 and an unusually wet season, site works are progressing according to schedule.
Major Milestones achieved are:
- Wash Water Tower Base Cast
- Quay Completed and ready for GEF Barge Installation
- GEF Barge #1 arrived on site www.damen.com
- Submarine Cables arrived on site www.hengtonggroup.com
- Contractor Site Establishment Containers arrive
- Workboats GAJU and MBOGO launched
- Liebherr 70t and 250t cranes on site
- Piling Rigs for Power Plant arrive on site
K56 Site – May 2020 |
The K56 Technical Team visit to Ywama Power Plant – Myanmar with CES |
Piling Rig on Site and ready to commence piling |
|
Wash Water Tower Foundation Bolts – Each Bolt weighs 38kg |
Assembly of Work Boat 2 |