    Construction Progress: July 2020

    30/07/2020

    Construction Progress: July 2020

    By Ivan A \ 0 Comment

    Despite the challenge of Covid-19 and an unusually wet season, site works are progressing according to schedule.

    Major Milestones achieved are:

    1. Wash Water Tower Base Cast
    2. Quay Completed and ready for GEF Barge Installation
    3. GEF Barge #1 arrived on site www.damen.com
    4. Submarine Cables arrived on site www.hengtonggroup.com
    5. Contractor Site Establishment Containers arrive
    6. Workboats GAJU and MBOGO launched
    7. Liebherr 70t and 250t cranes on site
    8. Piling Rigs for Power Plant arrive on site
    K56 Site – May 2020

    K56 Site – May 2020

    The K56 Technical Team visit to Ywama Power Plant – Myanmar with CES

    The K56 Technical Team visit to Ywama Power Plant – Myanmar with CES

    Piling Rig on Site and ready to commence piling

    Piling Rig on Site and ready to commence piling

     

    Wash Water Tower Foundation Bolts - Each Bolt weighs 38kg

    Wash Water Tower Foundation Bolts – Each Bolt weighs 38kg

    Assembly of Work Boat 2

    Assembly of Work Boat 2