The company reached its Commercial operations date on 17 February 2024, following the issuance of…
The project faced a major setback in the first quarter of 2022 when it was discovered that the mooring design of the FRSS…
With Covid-19 cases increasing substantially in Europe and South America over the past quarter, the accompanying lockdowns…
Construction on the Kivu 56 Methane Gas to Power Project showed good progress over the preceding six months.
Despite the challenge of Covid-19 and an unusually wet season, site works are progressing according to schedule.
SPLK achieved an important milestone with the ceremonial groundbreaking ceremony at the project site in October 2019.
SPLK has appointed local based company Fair Construction to undertake the civil and earthworks of the site.